Finances...

I am pleased to report that we have completed Phase 1 within our budget. Well under 5% has been spent on “administration” with all the rest going directly to the building work. The local community has greatly helped with free labour. However, we still need funding for the Second Phase of building starting in May 2008 after the rains, so please help if you can either through our secure on-line donation page or by mail using the Gift Aid form, I promise that the absolute maximum will again go to work on the ground.


Summary of Phase 1

Building is completed -

2 x double-classroom blocks

2 x urinals & hand-wash tanks

2 x double-pit latrines

2 x single-pit latrines

Borehole & pump

Admin building (3 rooms)

Teachers house (3 bedrooms)


Building Costs

Building Materials

Cost (£) Percentage of Total (%)
9,553 35


Travel and Transport (including local sand and brick collection, building material delivery from Mzuzu (30km), personnel movement to and from the site, air flights and fuel)

Cost (£) Percentage of Total (%)
10,734 40


Professional Labour (a relatively low figure due to local free labour from the community)

Cost (£) Percentage of Total (%)
5,848 22


Admin (including comms)

Cost (£) Percentage of Total (%)
487 2


Maintenance and Repairs

Cost (£) Percentage of Total (%)
255 1


TOTAL = £26,880


Capital Expenditure

Isuzu Double-Cab (now for sale) £4,170

Toyota Hilux £4,515

Remaining building materials valued at £300